Following a series of Kona Low storms, severe erosion along Kamehameha Highway at Waimea Bay sent boulders cascading onto the roadway, forcing a partial closure of one of Oahu's most heavily trafficked coastal routes. The State of Hawaii required immediate slope stabilization to protect public safety and restore full two-lane traffic. Prometheus Construction selected Vertical Worx, a utility helicopter operator, to execute precision aerial deployment of 23 geomesh netting panels — each 150 feet long, 12 feet wide, and weighing up to 1,800 pounds — delivered directly to crews staged on the cliff face via longline helicopter.


Critical Path Marketing (CPM) provided aerial drone and ground-based videography to document this time-critical operation in real time. Through this specialized production, Vertical Worx was able to capture verified proof of their precision load-placement capability, safety record, and ability to execute complex aerial rigging work under a compressed emergency timeline.


Learn how Critical Path Marketing delivers complex construction documentation solutions by visiting our Case Studies Page. 

Waimea Bay Slope Stabilization

Aviation Stabilization Infrastructure | Waimea Bay, Hawaii

Challenges

NordicPCL_Logo.png

Challenges

NordicPCL_Logo.png

Challenges

NordicPCL_Logo.png

Challenges

NordicPCL_Logo.png
Bucher Glass Sitka-24.jpg
CPM Value

Proof of Performance & Bid-Ready Asset | CPM delivered a complete visual record of the operation — aerial and ground footage capturing the speed, precision, and safety of the deployment: 23 panels secured, 40% of the cliff face stabilized, zero incidents, in a single day on a job estimated to take two weeks by conventional methods. This gave Vertical Worx a verified, field-tested demonstration of their precision aerial rigging capability.

The finished assets now serve as a marquee proof point for Vertical Worx's bid proposals, positioning the firm as the go-to aerial partner for contractors and government agencies facing time-sensitive infrastructure work in difficult terrain across Hawaii's construction and emergency response sectors.

Ka Haku-21.jpg
Challenges

Manned Aircraft Deconfliction & Rapid-Cycle Production | Documenting a live longline helicopter operation over an active highway and unstable cliff face required CPM to operate at the same tempo as the flight crew. With a 15-minute pick-to-release cycle and 23 panels moving in a single day, camera positions had to be repositioned continuously along the highway corridor without ever entering the helicopter's flight path or the active work zone below the cliff.

Every camera placement was coordinated directly with the Vertical Worx flight crew and Prometheus's site safety team under strict deconfliction protocols. With no opportunity for re-shoots, each of the 23 drops had to be captured correctly on the first attempt.